Springfield Suppliers Resumed Production at 002
"Springfield Assembly Plant will resume production the week of December 13th, 2010. MRP will run the week end of Nov 5th and suppliers should see 830 material releases deposited in their mailboxes for Monday morning November 8th. Suppliers are required to process and review their 830 [EDI] Releases being specifically consonant of the first bucketed requirement date. Additionally, year to date accumulated receipts were reset on Nov. 1st in accordance with Navistar's fiscal year end. Any and all questions regarding release requirements are to be routed to the Springfield Material Planning Group. Note, Sequence Suppliers will receive an 866 the morning of Nov 5th."